LaGuardia Airport Pedestrian Bridge B
Cody Builders Supply fabricated roof railings and miscellaneous metals for the new LaGuardia Airport Pedestrian Bridge B in 2020 (Southwest terminal). The Brooklyn Diner stainless steel cladding was a unique piece of work within Pedestrian Bridge B. The cladding has a custom non directional finish and unique geometry that had to be woven through pre-existing […]
Manhattan Excavation Support
Cody Builders Supply fabricated the steel bracing, walers and rakers to support the excavation at the Hudson Square site in New York for the new Walt Disney Company headquarters. The schedule was very challenging and stringent. Tap to enlarge
Piscataway Secondary Clarifiers WSSC
Cody Builders Supply fabricated curved aluminum launders, baffles, and weirs for the Piscataway Secondary Clarifiers WSSC project. These wrap around five clarifier tanks to allow the clean water to be separated from the dirty water. The challenges were acquiring the large volume of aluminum plate at a time when aluminum prices were very volatile and […]
US 183 Pedestrian Overpass Enclosures
On this design build project, special care and attention had to be taken to the welding sequencing and control of heat distortion due to the thousands of welds required on the enclosures. Cody also devised a means of attaching the curved “waves” to the sides of the enclosures so the different coating systems could be […]
Long Island Railroad Nostrand Avenue Rehabilitation
Cody provided complete supply of all structural, miscellaneous and ornamental metals for this project. Deliveries had to be staged with active traffic below the station and coordinated tightly with the erector. Cody overcame challenges in the anti-graffiti clear coating system and multiple coating systems to achieve the overall complete scope materialization.
SFMTA Central Subway Union Square Market Street Subway Station
Cody supplied over 150 Truckloads of fabricated steel permanent struts and wales for support of excavation for the Union Square Market Street subway station in San Fransisco, CA. We also provided the complete structural steel framing for the job including elevator towers at the UMS garage and station, stair framing, and planter framing. Cody’s scope […]
Enhanced Stations Initiative Package 2 ~ Four stations on the Astoria Line in Queens New York
Cody assisted with the design of the key components of the station by providing mock ups and renderings to the design team in advance of completed design information so as to keep up with the highly aggressive project schedule. Cody provided over 5,000 Linear feet of platform windscreen out of stainless steel with wire mesh […]
Oakland Zoo construction
The bison viewing area of the new California Trail exhibit at the Oakland Zoo. Slated to open in 2018. Cody Builders fabricated the circular canopy with the eagle flying above it.
NYCTA 2nd Avenue Subway 86th Street Station
Complete miscellaneous metals and structural steel for finishes. Complete Service Carrier system for mezzanine and platform levels, full metals supply for project with entrances and ancillary buildings Click to enlarge
South Sacramento Corridor Phase II
Year Completed: 2015 | Owner: Sacramento Regional Transit District | General Contractor: Balfour Beatty Infrastructure, Inc. | Sub Contract Value: $1,070,000 Subcontract Scope / Description of Work: Steel framing, handrails and complex architecturally exposed station canopies with integrated services. Click to enlarge